PADAMS MOULDS THE FUTURE

Profile picture

Our
Numbers
Speak

Our Key
Sectors

Banking
Healthcare
Airports
IT
E-Commerce
Co-Working Spaces
Warehousing
Factories
Real Estate
Infrastructure
Retail
Residential
Hospitality

Our Offices
in India

Maharashtra
Scroll to Explore Cities

Our
Fabrication
Units

Navi Mumbai

1,28,000 Sq. Ft.
Navi Mumbai Factory

Bangalore

1,05,000 Sq. Ft.
Navi Mumbai Factory

Delhi

50,590 Sq. Ft.
Navi Mumbai Factory

Hyderabad

50,000 Sq. Ft.
Navi Mumbai Factory

Executive

Leadership

Shankar Kularia

Director

Dharam Kularia

Director

Gunesh Joshi

COO

Core Team

Lalit Sharma VP

BD, Marketing & Tendering

Laxman Kularia VP

HR & Admin

Ankit Karal VP

Accounts

Debu Suthar VP

Procurement & Sourcing

Shiv Gepal VP

Banking & Finance

Gopal Head Billing

Operation Team

Pukhraj

VP Operations
All India

Vijay

Project Operations
North & East Region

G Ram

Quality Assurance

Mangesh

Head - EHS

Sameer

Project Operations
Hyderabad Region

Karthick

Project Operations
South Region

Atul

Head - MEP

Project Managers

Respective Sites

Design Team

Pankaj

VP Design & Build

Shivani

Design Support

Trusted by
Industry Leaders.

Awards &
Certificates

Guinness World Records

International Safety Award

Certificate for appreciation -
Robert Bosch Engineering & Business Solutions

Rajasthan Gaurav Award-2024

Maharashtra State Best Employer Brand Award 2023

Certificate of Achievement -
100 Million Safe Man Hours - 2023
Jio World CentreIndia's Greatest Brands 2021- 2022

India's Greatest Leaders 2021-2022

Bharat Gaurav Award 2021

Leading Luxury Interior Brand of the Year 2021

Bharat Youth Award 2021

Best Contractor of the Month -2018

Gyproc Trophy -2016

Project Excellence Award -
Carelon Global Solution

Safety Excellence Award

Certificate of Excellence -
Best General Contracting Firm

Certificate of Appreciation -
Samsung C&T 1.0 Million Safe Man Hours

Safety Performance Award -
Lonza Knowledge Centre - 750,000 Safe Man Hours

World Book of Records London -
15,000 KG Badamhalwa

Certificate of Appreciation -
200 Thousand Safe Man Hours

Business Icon -
Dubai Award

Dun & Bradstreet's Business Enterprises of Tomorrow

Ganga Award

Our Project
Portfolio

01 / 05
Standard

EHS Work
Procedures

Standard

EHS Work
Procedures

Safety First

Height Work
Process

Hazard Control

Hot Work
Process

EHS (Environment,
Health, Safety)

1

Safety Strategy

Safety Committee: Safety Heads (GC contractor, PMC, Client), Project Leads (GC contractor, PMC, Client representative)

2

Key Preventive Measures

Strict adherence to safety protocols, mandatory medical check-ups, and thermal scanning for all individuals entering the site.

  • Monthly Safety committee meeting
  • Overview on the EHS implementation and improvement
  • Strategize corrective actions
  • Safety Assurance team: Safety Managers
  • Fortnightly Safety assurance meeting
  • Discussion on gaps in safety implementation
  • Discussion on remedial actions
  • Formulation of tactical approach towards addressing gaps

  • Implementation:
  • Weekly Safety implementation meeting
  • Daily overview/review of tbt, observations, unsafe conditions...
  • Review of effectiveness of permit systems
  • Labor awareness programs
  • Infra-red non-contact thermometers / devices to be used for thermal screening
  • Social Distancing to be strictly maintained
  • Regular sanitizing of hands, Use of Automatic / Pedal Sanitizer system
  • Adherence to Safety protocols and use of proper PPE’s
  • All workers to undergo medical check-up for obtaining fitness certificate
  • All thermal scanning records / Entry-Exit Records to be maintained
  • Staggered pattern / batch wise to be followed while entry / exit
  • Security guards deployed at entrance points for constant checking
  • All necessary signages and posters will be displayed on site
  • Emergency contact to be displayed at site

Quality Compliance
Parameters

1

Material Inspection

Ensuring all incoming resources meet the specified standards and are stored correctly to prevent degradation.

2

Workmanship

Maintaining high standards of execution through rigorous checks and approved method statements.

3

Testing & Audit

Continuous verification through field tests, lab analysis, and regular audits to ensure compliance.

  • Establishing Skilled Benchmark Standard of Works throughout Execution
  • Inventions of New Ideas | On Site | Off Site Working Methodology
  • Submission of Quality Plan
  • Dedicated Involvement of experienced Quality Engg on Package wise Activity
  • Work Method Statement - Activity Wise
  • Quality Checklists – Activity Wise
  • Using of Quality Tools & tackles
  • Mock-up Works – Maintaining an Benchmark Execution
  • Monitoring | Auditing Execution
  • Adherence to approved method statements
  • Pre-pour inspections for concrete works
  • Checklist based inspection for all finishing works
  • Mock-up approval before mass execution
  • Regular toolbox talks on quality standards
  • Snag list preparation and rectification
  • Field testing of materials (Slump test, Cube test)
  • Third-party laboratory testing coordination
  • Internal Quality Audits (Weekly/Monthly)
  • Non-conformance report (NCR) tracking
  • Corrective and Preventive Actions (CAPA)
  • Final handover documentation and as-built drawings

Quality Assurance
& Control

1

Resource

Resource will be functioning independently to ensure the objective of QA is achieved.

2

Basis for Quality Control

Foundational documents and standards.

3

Inspection Stages

Key milestones for quality verification.

  • Deployment of full-time personnel on site for Quality Assurance & Control
  • Resource will be functioning independently to ensure the objective of QA is achieved.
  • Quality Plan & Manual
  • RFP Specifications, Approved Shop Drawings, GFC Drawings, Method Statements, Checklists
  • Design Aesthetics & Overall Functioning
  • Any quality observations will be addressed & best corrective action will be initiated.
  • Material Inspection & Approval
  • Inspection at Vendor’s place during the manufacturing process
  • Initial Level Inspection at site
  • Mid Stage Inspection at site
  • Final Inspection at the completion stage

Quality Implementation
Material

1

Material inspection at factory

Material inspection at factory (capital goods)

2

Material inspection at receipt

Material inspection at receipt in store

3

Installation method statement

Installation method statement and checklist

4

Tracking quality points

Tracking of the quality points on daily basis

  • Checks for performance, quality, readiness, etc.
  • Rejected material sent back to supplier
  • Test certifications (where applicable) upon delivery
  • On site calibrated checks (where applicable)
  • Workwise/Trade wise checklist
  • Checklist of quality as per room data sheet
  • Daily walk by Quality manager
  • Internal escalation to GC Contractors’ Project Director in case lapses in closure

Insurance & Labour

1

Insurance & Labour Compliance

Ensuring comprehensive insurance coverage and labor compliance from project inception.

2

Labor Attendance

Biometric attendance tracking and comprehensive documentation for all workforce.

3

Weekly and Monthly Documentation

Regular documentation and reconciliation processes for labor compliance.

4

Labor Compliance Audit

Quarterly audits to ensure ongoing compliance and address any gaps.

  • Obtaining insurance coverages as defined in RFP before on-site execution starts
  • Site registration in BOCW and labor licensing
  • Maintaining a dedicated resource at the site for labor documentation
  • Daily labor attendance through biometric (face reading) for all, including management teams, subcontractors, and nominated subcontractors
  • Reconciliation of the same on a weekly basis
  • Maintaining the labor wage register on-site, reconciliation every fortnight/month
  • Dedicated fortnightly meetings with respective contractors where there seems to be a gap in documentation
  • Maintaining the labor wage register on-site, reconciliation every fortnight/month
  • Dedicated fortnightly meetings with respective contractors where there seems to be a gap in documentation
  • Audit for labor compliance in each quarter
  • Closing the Audit observations (if any) within a fortnight

Quality
Compliance
Parameters

Ensuring excellence through rigorous standards and dedicated execution protocols.

Quality Management

Establishing Skilled Benchmark Standard of Works throughout Execution

  • • Inventions of New Ideas | On Site | Off Site Working Methodology
  • • Submission of Quality Plan
  • • Dedicated Involvement of experienced Quality Engg on Package wise Activity
  • • Work Method Statement – Activity Wise
  • • Quality Checklists – Activity Wise
  • • Using of Quality Tools & tackles
  • • Mock-up Works – Maintaining an Benchmark Execution
  • • Monitoring | Auditing Execution

Block works:

  • • Providing Sleeves in wall for above Ceiling Services Entry – In Coordination with BIM
  • • Providing Beam Bridge at Floor level for Services Entry– In Coordination with BIM
  • • Chiseling of Walls from External Surface for Access Control Cabling works

Internal Plaster | POP Punning

Waterproofing Works for PAC

False Flooring Marking & Services

Drilling & Supporting Works – To avoid Damages to Finished Epoxy Flooring

Above Ceiling Works

  • • Modular Ceiling Marking – Supporting
  • • Conduit & tray Works
  • • Cabling Works
  • • FA | PA | Rodent Cabling Works
  • • Chilled Water Copper Piping
  • • Pre-action Piping Works
  • • Plumbing drain Line Works

Temporary Door Installation

Painting base Coat Preparation

Epoxy Coating Works